- Reviewed status of Queen’s Courtyard work:
- More digging this week and concrete removal
- A/C unit out of Reception office and windows fixed
- Timing is on track (4 week expected time frame, one week done already)
- HVAC Status update:
- Ducting into Library and Receptionist office will be installed in the newly cored holes this week and will complete by Thursday.
- There will be hole patching
- The electrical team from Blackhawk may need to come back to fix the connection to the J box that got moved.
- Kathleen advised about the break in of 2/29/2020. Once police report is filed, she will share the photos and information about the theft with the team for their information.
- Next meeting will be on March 10, 2020. 9:15a in the Fireside Room.