Wednesday, March 4, 2020

Construction Updates March 4


  • Reviewed status of Queen’s Courtyard work:
    • More digging this week and concrete removal
    • A/C unit out of Reception office and windows fixed
    • Timing is on track (4 week expected time frame, one week done already)
  • HVAC Status update:
    • Ducting into Library and Receptionist office will be installed in the newly cored holes this week and will complete by Thursday.
    • There will be hole patching
    • The electrical team from Blackhawk may need to come back to fix the connection to the J box that got moved.
  • Kathleen advised about the break in of 2/29/2020.  Once police report is filed, she will share the photos and information about the theft with the team for their information.
  • Next meeting will be on March 10, 2020.  9:15a in the Fireside Room.