Wednesday, April 8, 2020

Construction updates April 8

We hadn’t met in several weeks so had a catch-up meeting.

Rocky Update:

  • Dumpsites closed for a few days due to rain so dirt removal on hold a few days.
  • They’re taking the down time to put a man lift in
  • Stairs to the Queen’s Courtyard concrete was poured incorrectly so demo is happening this week during the rain and next week when the rain subsides, they’ll re-pour the cement.
    • Discussion about the color of the courtyard red cement in conjunction with the new cement installation. Tom will go to review the site and see what the delineation looks like. Kathleen suggested we consider refreshing the red in the courtyard so there would be an even match from old to new and the team will look into a quote and scope of work for that.

Tom:

  • Asked to review the webcam for the site and review a distinctive wet area on the one panel of the shoring wall. Rocky and team will investigate further. It could be a blacktop run off issues, they’ll check it out.

Kathleen:

  • Thanks for a smooth power down and reboot. Only one issue arose with the back up battery on the magnetic locks on a few of our doors. We’ve chained the double doors into the courtyard for security. We checked into getting it fixed or being able to reboot it ourselves with our regular tech, but he advised it would require a site visit and he is quarantined and has been ill. Kathleen will check with the company who installed the system (JDS Security)and see if they can send someone else out to resolve the issue.

Brooks:

  • Inquired about the schedule of the erection of the crane and wondered if it would be delayed at all? Rocky advised that other than a few rain days delay it’s pretty much on the same schedule.
  • Any new graffiti? Just the stuff on the 6th Ave side in the tunnel, with a little on the green fabric fence. They’ll be addressing that today.